How Long Does It Take to Build a House in Kerala? Complete Timeline Guide

Understanding the house construction time in Kerala is essential because it helps you plan your budget, schedule, materials, and even your shifting date. The construction timeline can vary depending on design, approvals, weather, contractor experience, and material availability. However, most houses follow a predictable structure.

In this blog, we will break down the complete construction timeline, common delays, and expert tips to ensure your project finishes on time.

1. Average House Construction Time in Kerala

On average, a standard 1200–2000 sq. ft. house in Kerala takes:

⏳ 8 to 14 months to complete.

But this depends on many factors such as:

  • Budget
  • Design complexity
  • Construction company expertise
  • Site conditions
  • Weather (especially monsoon delays)
  • Approvals from local authorities

If you select an experienced and organized construction company, the house construction time in Kerala can be faster and more predictable.

2. Complete Timeline: Step-by-Step House Construction Process in Kerala

Here’s a clear breakdown of how long each stage usually takes:

Step 1: Planning & Architectural Design (2–6 Weeks)

Before construction begins, you need:

  • Site visit & survey
  • Floor plan creation
  • Structural design
  • 3D plan (optional)
  • Revisions & final approval

Time required: 2 to 6 weeks
Complex designs may take longer. Working with professional architects helps reduce errors and revisions.

Step 2: Building Permit & Government Approvals (3–8 Weeks)

This depends on:

  • Panchayat / Municipality rules
  • Plot documents
  • Layout approval
  • Environmental clearances (only in some cases)

Time required: 3 to 8 weeks

Delays mostly happen due to missing documents or technical mistakes. Choosing experienced builders helps speed up approval.

Step 3: Site Preparation & Foundation (3–5 Weeks)

This includes:

  • Site clearing
  • Marking
  • Excavation
  • Foundation work
  • Basement (if any)

Type of foundation (shallow / deep) affects timing.

Time required: 3 to 5 weeks

Step 4: Structure Work – Pillars, Walls & Roof (10–16 Weeks)

This is the longest and most important stage. It includes:

  • Pillars
  • Plinth
  • Brickwork
  • Lintel
  • Roofing
  • Concrete curing

Time required: 2.5 to 4 months

Curing time significantly affects the house construction time in Kerala, as humidity and monsoon slow down the process.

Step 5: Electrical & Plumbing Work (3–6 Weeks)

After the structure is ready:

  • Electrical wiring
  • Plumbing lines
  • Switchboards
  • Pipe fittings
  • AC provisions

Time required: 3 to 6 weeks

Doing electrical and plumbing together saves a lot of time.

Step 6: Plastering, Flooring & Tiling (4–6 Weeks)

This includes:

  • Interior plastering
  • Exterior plastering
  • Flooring tiles
  • Bathroom wall tiles

Time required: 4 to 6 weeks

Material shortages can cause delays, so pre-select tiles and materials early.

Step 7: Interior & Exterior Finishing (6–10 Weeks)

This is where the house transforms:

  • Painting
  • Ceiling works
  • Carpentry & woodwork
  • Modular kitchen
  • Door & window fittings
  • Wardrobes
  • False ceiling

Time required: 1.5 to 2.5 months

Interior finishing often decides whether your project gets delayed or stays on track.

Step 8: Final Cleaning, Inspection & Handover (1–2 Weeks)

Builders do:

  • Deep cleaning
  • Electrical testing
  • Plumbing testing
  • Leak inspection
  • Final quality check

Time required: 1 to 2 weeks

Total Estimated Construction Time: 8 to 14 Months

A simple home: 8–10 months
A premium or custom home: 12–14 months

This is the most accurate and practical timeline for the house construction time in Kerala.

3. Factors That Affect House Construction Time in Kerala

1. Weather Conditions

Kerala’s monsoon significantly slows down construction activities like curing, plastering, flooring, and outdoor work.

2. Contractor Experience

Experienced construction companies finish faster due to planned workflow.

3. Material Availability

Shortages of cement, steel, tiles, or wood can delay progress.

4. Design Complexity

Modern and luxury homes with curves, double heights, and custom features take more time.

5. Government Approvals

Delay in permits can push the project by months.

6. Labour Availability

Skilled labour shortages affect construction speed.

4. Tips to Speed Up House Construction in Kerala

Here are expert ways to reduce construction delays:

✔ Choose a professional construction company

Unorganized contractors cause 60% of delays.

✔ Finalize designs before starting

Avoid changes during construction.

✔ Select materials early

Tiles, bathroom fittings, and woodwork should be finalized in advance.

✔ Monitor progress weekly

Regular supervision keeps the project on track.

✔ Opt for turnkey construction

This offers faster completion because the builder manages everything.

5. Why Choose Master Plan Builders for Fast & Quality Construction?

If you want predictable and efficient house construction time in Kerala, Master Plan Builders is a top choice because:

  • 7+ years of experience
  • 200+ completed projects
  • Skilled engineers & interior designers
  • On-time delivery guarantee
  • Transparent pricing
  • High-quality materials
  • Turnkey construction solutions

They manage every stage efficiently, ensuring you get your dream home on time and within budget.

Conclusion

Understanding the house construction time in Kerala helps you plan better and avoid unnecessary stress during your project. On average, building a home takes 8 to 14 months, depending on design, approvals, and material availability. With expert planning and the right construction company like Master Plan Builders, the entire process becomes faster, smoother, and hassle-free, ensuring timely delivery without compromising on quality.